To view filtered minutes, replace the Gantt diagram with an extract of the minutes:
1.Add the column Tasks in Gantt in the Minutes (refer to How to Add Columns) and fill it by double-clicking the cells
2.Select a task in the planner
3.In the diagram, right-click and select Show Gantt minutes (alternatives: flip button Minutes, double-click the bar); this shows the minutes whose column Tasks in Gantt is filled with the task name
4.To revert to the diagram, press F4 (alternative: flop button Planner)
5.To revert to the minutes, press F4 again (alternative: flip button Minutes)
NOTES
- If the tasks has bee assigned in the WBS, no Minute shows
- Minutes with several occurrences show as a set as in the Nomenclatures.
This view features a bottom pane that can be configured apart from the Minutes bottom pane. Refer to How to Access the Minutes and How to Build the Bottom Panes.
The titles inside a section of minutes show as collapsed groups (sign +).
To colorize some rows, refer to How to Change the Font or Layout.
QUANTITY
The quantity column shows the overall quantities.
Two columns can be inserted:
▪Quantity in option: quantity of a minute whose parent task is an option (a blank cell means generally that this is not an option)
▪Quantity in minutes: quantities in minutes (editable)